木工加工棚完工后的檢查
來源:http://kshyinuo.com/ 發(fā)布時間:2023-01-03
木工加工棚完工后該如何進行檢查與驗收呢?下面跟隨小編一起來看看吧!
How to conduct safety inspection and acceptance after the completion of woodworking shed? Now follow Xiao Bian to have a look!
1.總平面設計
1. General layout design
指定原材料加工區(qū),半成待檢產(chǎn)品存放區(qū),半成待檢產(chǎn)品存放區(qū),成品合格區(qū)垃圾收集區(qū),離地30cm的扶壁建在原材料圍欄的存放區(qū),間距2.0m,按照規(guī)格型號隔離堆放。
The designated raw material processing area, half product storage area for inspection, half product storage area for inspection, garbage collection area for qualified finished products, and buttresses 30cm above the ground are built in the storage area of raw material fence with a spacing of 2.0m, and are stacked separately according to specifications and models.
2.標志和標志的布局
2. Sign and sign layout
(1)各種原材料堆放標志牌,各種待檢工作區(qū),合格產(chǎn)品標志牌應配備齊全。焊接和切割鋼筋時,應設置特殊的危險警告標志,以防止氧氣和乙炔的易燃易爆。安臨時用電警示標志安生產(chǎn)、消防、等安,全文明施工標志。
(1) The signboards for stacking various raw materials, various work areas to be inspected, and the signboards for qualified products shall be complete. When welding and cutting reinforcement, special danger warning signs shall be set up to prevent oxygen and acetylene from being flammable and explosive. Warning signs for temporary electricity use Safety signs for production, fire protection, environmental protection, and civilized construction.
(2)鋼筋加工棚平面布置圖,加各種鋼筋結(jié)構(gòu)尺寸示意圖,各種鋼筋尺寸誤差標準要求圖。
(2) Layout plan of reinforcement processing shed, plus schematic diagram of various reinforcement structure dimensions, and standard requirements diagram of various reinforcement size errors.
(3)管理人員、質(zhì)量檢查員和操作人員的職責和制度。
(3) Responsibilities and systems of management personnel, quality inspectors and operators.
(4)鋼筋加機械設備操作規(guī)程等。
(4) Operating procedures for reinforcement and mechanical equipment, etc.
3.臨時用電
3. Temporary electricity
(1)加工棚內(nèi)使用的管道須使用合格的材料,不得使用廢料;施工現(xiàn)場架設電力線路應嚴格遵守相關(guān)要求和規(guī)定,確保線路安完整、美觀;
(1) The pipes used in the processing shed must be made of qualified materials, and waste materials are not allowed to be used; The erection of power lines at the construction site shall strictly comply with relevant requirements and regulations to ensure the safety, integrity and beauty of the lines;
(2)電源和照明線路須分開,配電箱內(nèi)的多路配電應標明門、鎖和防雨措施;臨時用電符合規(guī)定,因此須采用TN-S接零保護系統(tǒng),須實現(xiàn)三級配電二級保護和“一機一箱一閘一漏”保護措施。
(2) The power supply and lighting lines must be separated, and the multiple distribution in the distribution box should be marked with doors, locks and rainproof measures; The temporary power supply meets the requirements, so TN-S neutral connection protection system must be adopted, and three-level power distribution two-level protection and "one machine, one box, one switch and one leakage" safety protection measures must be realized.
(3)夜間施工要保證照明設施和足夠的亮度。
(3) Lighting facilities and sufficient brightness shall be guaranteed for night construction.
以上內(nèi)容主要講解了木工加工棚檢查與驗收,本期文章講解到這里就結(jié)束了,更多精彩內(nèi)容可以來我們網(wǎng)站http://kshyinuo.com進行咨詢了解!
The above content mainly explains the safety inspection and acceptance of the woodworking shed. This article ends here. More wonderful content can be found on our website http://kshyinuo.com Ask about it!
- 上一篇:圍擋護欄安裝不符合標準的方案
- 下一篇:工地圍擋是否能保護人們的?